Construction Progress

September 2026
On 12 October, construction works will begin in the northern part of the Göttingen campus. Work will initially focus on setting up the site and carrying out groundworks for the main building, which will be situated next to the New Greenhouse. Work on the LivestockLab, opposite the Veterinary Institute, will begin a little later.

June 2026
Building permission has been granted. The tenders for the first trades can now be published. Meanwhile, detailed execution planning continues in order to finalize the specifications for room and laboratory equipment.

May to July 2026
Preparatory work for connecting the LivestockLab to utilities is taking place on Burkhardtweg. This requires a temporary closure of the street. Bus services will be rerouted via Otto-Hahn-Straße.

February 2026
The construction site for the LivestockLab has been cleared. Construction is scheduled to begin here in October.